Wison Successfully Delivered its First Batch of Stick Built for RPLC Refinery Project

Release time:2015-04-21

SHANG HAI, China (21 April 2015) Wison Offshore & Marine Ltd. (Wison Offshore & Marine) announced today the delivery of its first batch of stick built for the key modularized components construction of the Petroleos De Venezuela, S.A.(PDVSA) RPLC refinery project, achieving an important project milestone which demonstrated the strong capabilities of Wison Offshore & Marine in module fabrication.

This is part of the contract awarded by Hyundai-Wison consortium (a consortium of Hyundai Engineering & Construction Co. Ltd., Hyundai Engineering Co.,Ltd. and Wison Engineering Ltd.) to supply key modularized components including pipe racks and equipment modules. Under the contract, Wison Offshore & Marine is responsible for the shop drawing, material procurement, construction, pre-commissioning and load out. 

There are altogether 94 modules and stick built totaling about 22,840 tonnes, which are to be delivered in 10 batches. While the first batch of stick built had been delivered, the module assembly has already commenced on 15th March 2015 at the same time and the first batch of modules shall deliver in July 2015 followed by progressive delivery with an interval of one month per shipment. The entire project shall complete in the first half year of 2016 as requested by the clients.

“Backed by the strong support from our clients and other stakeholders, the remarkable progress is the result of hard work from our project team.” Said Mr. An Wenxin, Senior Vice President of Wison Offshore & Marine. “We’re quite confident in the on-time and quality delivery of the entire project, with which we’ll once again prove ourselves as a global premier large modular supplier.”